Arizona Marina

Project:  50-year old marina and resort on the riverfront was demolished and a new $14 million resort, Topock was built to include a vinyl seawall, hotel, pool and spa with a marina, restaurants and more.

Solution: Truline vinyl sheet pile seawall filled with concrete and steel was selected to support the upland infrastructure and transition to the floating dock system. In addition, Truline was chosen for its clean aesthetics and long service life. After the concrete seawall was approved by the U.S. Army Corps of Engineers, construction began with the hybrid system, which allowed installers to construct a strong 8” poured-in-place concrete seawall with vinyl protection.

marina seawall Truline system

Location:  Near Lake Havasu, AZ
Owner:  Topock Route 66 Marina Resort
Architect:  Pontious Architecture
Contractor:  Running Bear Development
Length of wall:  700 LF (800 series)
Length of sheet piles:  14 ft.

marina seawall Truline
marina seawall Truline system
marina seawall Truline system